Executive Manager

Name: N. Sayadi
Education: Bachelor of Electrical Engineering (Isfahan University of technology)
Experience and research:
More than 14 years working about power quality and its effects on industries and electrical networks.
۱- Lighting and electrical service in the Mobarakeh Steel Company-Isfahan (Energy-Kar Company – 1997 to 1999)
۲- evaluate, design and construct of PMDC Motor of more than one hundred under-load sectionalisers (Isfahan Regional Electricity – 1999 to 2001)
۳- Power quality measurement and analysis for 100 large consumers at Tehran sub-transmission network (2001)
۴- Power quality measurement and analysis and evaluate the harmonics status of Isfahan tile factory (2001
۵- Power quality measurement and analysis and evaluate the harmonics status and provide solutions (Zarif-Mosavar company 2001)
۶- Assistance of codification Standards for safety devices of earth leakage current (switches protect) – Tavanir company (2002)
۷- Power quality measurement and analysis for large consumers at Isfahan sub-transmission Network (2003)
۸- Power quality measurement and analysis at 100 points in Isfahan MV and LV networks (2004).
۹- Power quality measurement and analysis at 56 points in Fars electrical networks (Fars Regional Electricity company 2003)
۱۰- Power quality measurement and analysis at 40 points in Kerman electrical networks (Kerman Regional Electricity company 2003)
۱۱- Power quality measurement and analysis at 44 points in Khouzestan electrical networks (Khouzestan Regional Electricity company 2004)
۱۲- Power quality measurement and analysis at 30 points in Yazd electrical networks (Yazd Regional Electricity company 2004)
۱۳- Power quality measurement and analysis at 47 points in Khorasan electrical networks (Khorasan Regional Electricity company 2004)
۱۴- Assistance of codification Standards for safety devices of earth leakage current (switches protect) Tavanir company (2004)
۱۵- Power quality measurement and analysis at 50 points in Bakhtar electrical networks (Bakhtar Regional Electricity company 2005)
۱۶- Power quality measurement and analysis at 56 points in Azerbaijan electrical networks (Azerbaijan Regional Electricity company 2005)
۱۷- Power quality measurement and analysis at 50 points in Semnan electrical networks (Semnan Regional Electricity company 2005)
۱۸- The energy audit in the industries of Azerbaijan (Idem factory, piston and bearing of Tabriz, Ardebil Industries 2005)
۱۹- Power quality measurement and analysis at 65 points in Isfahan electrical networks (Isfahan Regional Electricity company 2005)
۲۰- Power quality measurement and analysis at 100 points in Isfahan electrical networks (Isfahan Regional Electricity company 2005)
۲۱- measurement and analysis of parameters of arc furnace SVC at Mobarakeh Steel company (2005)
۲۲- investigate the causes of joint bursting of 63KV feeder cable at Mobarakeh Steel Company (2005)
۲۳- Power quality measurement and analysis at 100 points in Bakhtar electrical networks (Bakhtar Regional Electricity company 2006)
۲۴- Power quality measurement and analysis at 100 points in Isfahan electrical networks (Isfahan Regional Electricity company 2007)
۲۵- Power quality measurement and analysis at 60 points in Gharb electrical networks (Gharb Regional Electricity company 2007)
۲۶- Power quality measurement and analysis at 12 points in Kashan sub-transmission network (Daneshmand company 2007)
۲۷- Power quality measurement and source detection of disturbances at Gilan steel company and provide practical solutions (2007)
۲۸- Power quality measurement and analysis at 52 points in Mobarakeh steel company electrical network (2007)
۲۹- Earthling Evaluation of 230 kV Shahreza, 63 kV Farah-abad, and Isfahan university of technology sub-stations (2007)
۳۰- Power quality measurement and analysis at 55 points in Gharb electrical networks (Gharb Regional Electricity company 2007)
۳۱- Losses reduction of distribution networks project (Tavanir company 2007)
۳۲- Power quality measurement and analysis for Industrial, commercial, and residential consumers at 38 points in Tabriz electrical network (2007)
۳۳- Power quality measurement and source detection of disturbances at 400/230/63 kV Shahid-Montazeri substations (2007)
۳۴- Power quality measurement and analysis at 70 points in Fars sub-transmission networks (Fars Regional Electricity company 2007)
۳۵- Power quality measurement and analysis at 40 points in Kurdistan electrical networks (Gharb Regional Electricity company 2008)
۳۶- optimal capacitor placement in the Likak and Ghale-raeisi feeders to loss reduction and improve voltage profile (electricity distribution company of Kohgiluyeh and Boyer Ahmad 2008)
۳۷- optimal capacitor placement in the Daran feeder to loss reduction (electricity distribution company of Charmahale Bakhtiari 2008)
۳۸- Power quality evaluation for an oil company in Oman (2008)
۳۹- Power quality measurement and source detection of disturbances for 52 industrial consumers at electricity distribution company of Ghazvin (2008)
۴۰- Power quality measurement and source detection of disturbances for Polo-Film company (Qazvin 2008)
۴۱- Engineering services in order to identify cause of capacitor banks burning (Apadana Ceram company-Qazvin 2008)
۴۲- Power quality measurement and analysis at 24 points in Kurdistan sub transmission network (Gharb Regional Electricity company 2010)
۴۳- Power quality measurement and analysis at 125 points in Khuzestan sub transmission network (Khuzestan Regional Electricity company 2010)
۴۴- review causes damage to 400KV transformer of Saba steel company (Mobarakeh Steel company 2010)
۴۵- Power quality measurement and analysis at 3 HV/MV substation feeders in Kurdistan network (Gharb Regional Electricity company 2010)
۴۶- Evaluation of switching and transient effects on power transformers of Mobarakeh Steel company (2010)
۴۷- Evaluate causes of burning of dry distribution transformers of Apadanaceram company-Qazvin (2010)
۴۸- optimal capacitor placement and technical and economic studies on the electricity distribution network in Tabriz (2010)
۴۹- study on mitigation of voltage fluctuations in Kavan and Mahkar feeders using series capacitor- Alborz Power Distribution (2010)
۵۰- mitigation of voltage and current unbalances in petrochemical of Ghaed-Basir of Golpayegan (2010)
۵۱- design and construction of passive harmonic filter to solve the problem of burning and overheating capacitor banks and reduce the voltage and current harmonics injected to upstream network (Apadana Ceram company-Qazvin 2011)
۵۲- investigate the causes of the damage of 33KV PTs, Mahshahr Petrochemical (2011)
۵۳- mitigation of inrush current of arc furnace power transformers in Mobarakeh Steel company (2011)
۵۴- Power quality measurement and analysis at 4 HV/MV substaion feeders in Kermanshah and Ilam electrical networks (Gharb Regional Electricity company 2011)
۵۵- Power quality measurement and analysis for Industrial, commercial, and residential consumers at 38 points in Hormozgan distribution network (2011)
۵۶- investigate the causes of the damage of 230/33 kV power transformers of Hormozgan steel company (2011)
۵۷- Asses the role of voltage management on economic of distribution system and its technical effects in Bazaar-Tehran (2011).
۵۸- Power quality measurement and source detection of disturbances at 69 points in Semnan electrical network (2011)
۵۹- Power quality measurement and analysis at 72 points in Khorasan electrical networks (2011)
۶۰- Power quality measurement and analysis to determine the causes of damage to low voltage capacitors (400 v) and offer practical solutions (Mesbah Energy Company 2012)
۶۱- Design and optimize power system of Shahid-darvishi company-Bandar Abbas (2012)
۶۲- Power quality measurement and source detection of disturbances at Kabkan steel company-Mashahd (Moniran company 2012)
۶۳- Power quality measurement and analysis at MV feeders of HV/MV substation of Esfarayen steel company in order to adjust the SVC (2012)
۶۴- Power quality analysis at Electrical network of Sarakhs Refinery (2013)
۶۵- investigate the causes of the damage of cables of Shazand Refinery (2013)
۶۶- Protective Relay replacement of two generator sets at Imam Khomeini refinery Shazand (2013)
۶۷- power quality measurement and analysis of Sadr steel company-Lorestan (2014)
۶۸- investigate the earthling System and cause of damage to MV cables at GharbeAsia steel company (2014)
۶۹- power quality measurement and analysis to determine the source of voltage functions (paya-polymer Company-Qazvin 2014)
۷۰- modeling of a partial electrical network of Mobarakeh Steel company in order to optimize the consumption of electrical energy, and power quality and protection system (2014)
۷۱- Adviser of Tehran electricity distribution company for power quality and determine the concurrency factors of residential consumers. (2011-2014)
۷۲- Assistance of codification Standards for power quality (Tavanir company 2014)
۷۳- design, construction and operation of passive filters for Abadan refinery (Tiv energy company 2014)
۷۴- design, construction and operation of RC filters to improve voltage transients at Imam Khomeini refinery (consortium company structure 2014)